Arc Surveying & Mapping, Inc. provided pre and post dredge surveys on a contaminated sediment restoration project in Miami, Florida.

Arc provided hydrographic surveys behind dredging operations to assure compliance with City of Miami and Department of Environmental Regulations requirements.



Arc Surveying & Mapping, Inc. provided pre and post dredge surveys on a contaminated sediment restoration project in Miami, Florida.

Arc provided hydrographic surveys behind dredging operations to assure compliance with City of Miami and Department of Environmental Regulations requirements.


...


The dredging costs for this project were very high since the contractor had limited access, narrow and shallow tidal waters.

The excavated sediments were placed in containers and trucked to a disposal site.

Arc also performed the design survey many years previous for CH2M Hill and the City of Miami.

Cross-sections, probes and vibracore results were utilized to determine native bottom and the quantities of contaminated sediments to be excavated.